Dashboard Folders for Jira

Associate Dashboard to Project (Project Dashboard)

This feature is restricted to Jira Administrators, Dashboard Folders Administrator and Project Administrators only

Project Dashboard is a new feature that allows each Dashboard to be associated with multiple Project(s).

The associated Dashboard appears as links on the project sidebar.  

This makes it easy for end user to find all the project related Dashboards.

project sidebar border.png

Instruction

  1. Navigate to the target Dashboard page to associate to a Project

  2. Click on the "More" (…) icon from the Dashboard page

  3. Click on Link Dashboard to Project(s), the page will be redirected

    link to project border.png
  4. In "Link Dashboard to Project(s)" page 

    1. Associate Dashboard to Project:

      1. Enter the project name into the search box under “Project” column

      2. Select the target Project from the search result

      3. (Optional) Enter an Alias name for the Dashboard under “Alias Name for Dashboard” column

      4. Click on "Add"

        project dashboard - add.png


    2. Edit Alias Name of Project Dashboard:

      1. Click on the Alias name to add/edit

      2. Modify the Alias name wording

      3. Click on “Update”

        project dashboard - edit.png
    3. Delete Dashboard to Project Association:

      1. Mouse over the target Project in the list of Project(s)

      2. Click on “Delete” corresponding to the Project

        project dashboard - delete.png

Alias Name (if set) will be displayed instead of the original Dashboard name in the associated project sidebar. e.g.

project dashboard - alias.png

Permission

Jira Administrator

  • See all projects

Dashboard Folders Plugin Administrators

  • Only projects where user has Browse or Adminstrators role to

Jira Project Admin

  • Only user that holds Project Administrators role for at least 1 project

  • Only add/delete for the respective project(s) that user has Administrators role to


Why use Alias instead of Dashboard Names for Project Dashboards

  1. To shorten the name for easier readability

    • Dashboards typically have longer names to explain the purpose, project association and ownership as well to facilitate management

    • A best practice is to prefix/suffix the dashboard names with the Jira project key

    • However the relationship with the project becomes implicit when the dashboard appears in the Jira project’s sidebar. It is possible to have a shorter name

  2. To change the ordering